Hydraulic Power Unit for marine cranes - C5 Very High Anti-corrosion

165 kW, high-dynamic electrode regulation and dedicated accumulation

Sector: Marine / Offshore | Product: Hydraulic Power Unit (HPU) | Lead time: 12 weeks

Anti-corrosion protection

Tank volume

Installed power

The project

An international operator in the marine sector entrusted us with the complete design and construction of a hydraulic power unit for a large crane, operating in a maritime environment with high exposure to salt spray and humidity.

The order featured three non-negotiable constraints:
• C5 Very High anti-corrosion protection according to ISO 12944, with certified durability exceeding 25 years
• Delivery of the tested supply ready for installation within 12 weeks of the order — a lead time significantly lower than the industry average for supplies with C5 VH treatment
• Complete technical documentation included: hydraulic diagram, wiring diagram, operating manuals, and certifications

[Photo: overview of the completed power unit in the workshop, before shipping]

Technical data sheet

Feature Detail
Application Large-scale marine crane
Installed power 2 x 250 kW
Main pump flow rate 2 x 320 l/min @ 400 bar
Tank volume

~ 2,000 liters

Filtration

On return, 10 µm

Cooling

Water-cooled, 6 heat exchangers

Anti-corrosion protection

C5 Very High (ISO 12944) — durability > > 25 years

Operating temperature

-20 °C … +50 °C

Lead time

12 weeks (from order confirmation to testing)

How we approached the project

  1. Review and optimization of hydraulic diagrams

Starting from the diagram provided by the client, our technical department conducted a thorough review of the circuit together with the client's technicians and quality department. The analysis made it possible to identify margins for optimization on the unit's performance and to resolve some critical issues before the construction phase — avoiding changes during the work that would have compromised the schedule.

  1. Construction and assembly

Complete assembly of the HPU in our Portogruaro workshop, using premium components certified for marine applications. Each assembly phase was carried out in strict compliance with dimensional tolerances and industry regulations, with documented intermediate checks.

  1. C5 Very High anti-corrosion treatment

The surface protection cycle was managed through a specialized certified supplier: sandblasting to SA 2½ grade and painting compliant with ISO 12944-6 in the Very High durability category (C5 VH), specific for high-salinity marine environments. Direct coordination between our technical office and the coating specialist guaranteed compliance with deadlines without compromising the quality of the cycle.

  1. Complete functional testing

The unit was subjected to a testing program that included:

  • Pressure test at 400 bar
  • Functional and leak tests on the entire circuit (320 l/min, 250 kW)
  • Execution of the test in the presence of the client, with joint verification of parameters
  • Release of the complete testing dossier: protocols, results, material certifications, and painting certifications

Further information

Hydraulic Power Units (HPU)

Discover

Iron and Steel Industry Sector

Discover

Technical Office and Engineering Quality

Discover

Do you have a similar project? Contact the technical office with your specifications — we will propose a tailor-made solution.

Centrali per colata continua

Power units for continuous casting machines

Soft reduction, Performance Level D safety, and future line expandability